How to close the month across multiple LLCs

Pine Court LLC is holding up the February report. Its bank statement arrived Thursday instead of Tuesday, and portfolio sign-off moved from March 5 to March 9. A close calendar shows who’s waiting, what they can finish now and when the owner can expect the report.

A worked close calendar for 2 property LLCs

In this illustrative February 2026 close, Cedar Row LLC and Pine Court LLC report to one owner. Business Day 1 is Monday, March 2. The controller signs the portfolio package after both properties’ cash has been reconciled and the transfer between them ties out.

February 2026 close calendar
HandoffOwnerExpectedActual
Send both property trial balancesProperty manager (Day 1) (Day 1)
Send Cedar Row’s bank statementProperty manager (Day 2) (Day 2)
Send Pine Court’s bank statementProperty manager (Day 2) (Day 4)
Reconcile Cedar Row’s bank accountBookkeeper (Day 2) (Day 2)
Reconcile Pine Court’s bank account and tie out the transferBookkeeper (Day 2) (Day 4)
Review the cash schedules and transfer supportSenior accountant (Day 3) (Day 5)
Sign off on the portfolio packageController (Day 4) (Day 6)

Sign-off slipped 2 business days. Pine Court’s statement was due Tuesday, March 3 (Day 2) and arrived Thursday, March 5 (Day 4). The bookkeeper reconciled Pine Court and tied out the transfer the same day.

The senior accountant reviewed the cash schedules and transfer support on Friday, March 6 (Day 5). The controller signed off the next business day, Monday, March 9 (Day 6), instead of Thursday, March 5 (Day 4).

Keep Cedar Row moving

The property manager can send both trial balances on Day 1. The bookkeeper can finish Cedar Row’s bank reconciliation on Day 2 because its statement is in. Pine Court’s missing statement blocks the checks that need it. Put those items on hold, keep working on Cedar Row, and flag the dependency to the controller.

In the open items list, record who is getting the Pine Court statement and the next check-in. If your lender or investor package is due before both LLCs can close, tell the owner what’s outstanding and set a new delivery date. Leave portfolio sign-off open until the checks it depends on are complete.

Tie out both sides of the transfer

Match what Cedar Row recorded as due from Pine Court with what Pine Court recorded as due to Cedar Row. Put the sending and receiving entity, transfer date, amount and source reference on the same line. If only one side posted, put the difference and its owner in the open items list. The bookkeeper records the correction after approval.

Use the calendar for your next close

  1. List every entity and mark which reports, bank statements and loan statements come from someone outside the close team.
  2. Give every handoff one owner, an expected date and a place to record the actual date. Mark which tasks can run in parallel.
  3. Agree on who can approve adjustments and who signs off. Keep any open differences in a list that travels with the package.
  4. After sign-off, check which handoff pushed the date back. Adjust the next calendar around the work that actually moved it.

For a backlog, use the close repair guide to check how far back you need to go. If you need help with apartment portfolio books, see multifamily accounting services.